Construction Projects & Updates

  • As of March, 24, 2024

    Aragon | Burlingame | Capuchino | Hillsdale | Mills | Peninsula | San Mateo

    Aragon High School

    View AHS map

    Summer Projects: 

    • The parking lot adjacent to the tennis courts will be fenced off.

    • The site will be without power for an estimated 4-week period while the new switchgear is installed.

    • Construction of the Baseball & FlexField is slated for completion in Summer 2024.

    • The parallel parking spaces along the fire lane exit onto Alameda de las Pulgas will have traffic of heavy machinery.

    • The site will have new fire alarm panels and HVAC controls installed as part of the District Wide Fire Alarm Replacement & HVAC Controls Projects.
    • Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.

    Burlingame High School

    View BHS Map

    Summer Projects: 

    • Construction of the new gymnasium will occur through the summer.

    • Renovation of the music classroom and HVAC replacement of building C HVAC is slated to be completed at the end of summer 2024.
    • The site will have new fire alarm panels and HVAC controls installed as part of the District Wide Fire Alarm Replacement & HVAC Controls Projects.
    • Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.

    Hillsdale High School

    View HHS Map

    Summer Projects: 

    • Phase III of the Transite Encapsulation Project is slated for completion in the summer of 2024.

    • Construction completion for the tennis courts is slated for the end of summer 2024.

    • The site will have new fire alarm panels as part of the District Wide Fire Alarm Replacement Project.
    • Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.
    • Switchgear replacement is slated for the summer of 2025.

    Mills High School

    View the MHS Map

    Summer Projects: 

    • Phase II of the Transite Encapsulation Project is to begin and be completed in the summer of 2024.
    • The site will be without power for an estimated 4-week period while the new switchgear is installed.
    • The site will have new fire alarm panels and HVAC controls installed as part of the District Wide Fire Alarm Replacement & HVAC Controls Projects.
    • Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.

    San Mateo High School

    View the SMHS Map

    Summer Projects: 

    • Construction of a new gym began in September 2023. Construction is ongoing this summer of 2024, and completion is slated for April 2025.

    • The site will have new fire alarm panels and HVAC controls installed as part of the District Wide Fire Alarm Replacement & HVAC Controls Projects.
    • The tennis courts and baseball improvement work is slated for completion in the summer of 2024.

    • Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.