Construction Updates
As of March, 2025
Summer Projects:
-
The site will be without power for an estimated 4-week period while the new switchgear is installed.
-
The site will be on fire watch during the replacement of the fire alarms.
-
The parallel parking spaces along the fire lane entrance onto Alameda de las Pulgas will have two-way traffic of heavy machinery.
- The site will have new fire alarm panels and HVAC controls installed as part of the District Wide Fire Alarm Replacement & HVAC Controls Projects.
- Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.
Summer Projects:
-
Construction of the new gymnasium is slated for completion late July / early August
- Building C HVAC and roof replacement is slated to be completed at the end of summer 2025.
- The site will have HVAC controls installed as part of the District Wide HVAC Controls Projects.
- Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.
- The stadium lights will be replaced with LED lighting and the track will not be accessible or available for use during construction.
- The nutrition services department will be upgrading the school kitchen over the Summer.
Summary Projects:
- Construction of the Solar Canopies and EV Charging Stations requires closure of the front entry of the school as a safety precaution.
- HVAC Controls replacement postponed to Summer 2026.
Summer Projects:
-
Replacement of the chillers on buildings J&K will impact ventilation and cooling.
-
The nutrition services department will be performing upgrades in the kitchen in the summer.
- The site will be on fire wat through construction for the new fire alarm panels as part of the District Wide Fire Alarm Replacement Project.
- The switchgear foundation will be poured Summer of 2025 and construction for the remainder of that work will continue Summer of 2026.
- The Hillsdale HS monument project is in design and will have no impact to the site.
Summer Projects:
- The site will have new HVAC controls installed as part of the District Wide HVAC Controls Projects.
- Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.
- The nutrition services department will be performing upgrades in the kitchen in the summer.
- The Switchgear Project is postponed to Summer2026.
Summer Projects:
-
Construction of the new gym is slated for completion in May 2025.
- The site will have new HVAC controls installed as part of the District Wide HVAC Controls Replacement Project.
- The San Mateo High School Kiln Project will take place beginning June 2, 2025, and is slated for completion at the end of the Summer.
- Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.
- The parking stalls between the new gym and tennis courts will be re-striped.
- The Bridge Academy Portables will be installed in May 2025.
- The Venus and Saturn rooms will be modernized at the adult school during the Summer of 2025.
- The transportation yard will be impacted by the installation of EV bus charging stations and install and energization of new switchgear.