Construction Updates

As of May 4, 2024

Aragon | Burlingame | Capuchino | Hillsdale | Mills | San Mateo

Aragon High School

AHS Aerial Map of Construction

Summer Projects: 

  • The parking lot adjacent to the tennis courts will be fenced off.

  • The site will be without power for an estimated 4-week period while the new switchgear is installed.

  • Construction of the Baseball & FlexField is slated for completion in Summer 2024.

  • The parallel parking spaces along the fire lane exit onto Alameda de las Pulgas will have traffic of heavy machinery.

  • The site will have new fire alarm panels and HVAC controls installed as part of the District Wide Fire Alarm Replacement & HVAC Controls Projects.
  • Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.

Burlingame High School

BHS Aerial Map of Construction

Summer Projects: 

  • Construction of the new gymnasium will occur through the summer.

  • Renovation of the music classroom and HVAC replacement of building C HVAC is slated to be completed at the end of summer 2024.
  • The site will have new fire alarm panels and HVAC controls installed as part of the District Wide Fire Alarm Replacement & HVAC Controls Projects.
  • Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.

Capuchino High School

CHS Aerial View of Construction Projects

Summary Projects:

  • No major construction taking place
  • Backstop safety netting at the Baseball field
  • Solar Canopies
  • Public Facing EV Charging Stations
  • HVAC Controls (District Wide)
  • Fire Alarm Replacement: Work will take place on a swing shift to accommodate Summer School.
  •  

Hillsdale High School

HHS Aerial View of Construction Projects

Summer Projects: 

  • Phase III of the Transite Encapsulation Project is slated for completion in the summer of 2024.

  • Construction completion for the tennis courts is slated for the end of summer 2024.

  • The site will have new fire alarm panels as part of the District Wide Fire Alarm Replacement Project.
  • Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.
  • Switchgear replacement is slated for the summer of 2025.

Mills High School

MHS Aerial View of Construction Projects

Summer Projects: 

  • Phase II of the Transite Encapsulation Project is to begin and be completed in the summer of 2024.
  • The site will be without power for an estimated 4-week period while the new switchgear is installed.
  • The site will have new fire alarm panels and HVAC controls installed as part of the District Wide Fire Alarm Replacement & HVAC Controls Projects.
  • Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.

San Mateo High School

SMHS Aerial View of Summer Construction Projects

Summer Projects: 

  • Construction of a new gym began in September 2023. Construction is ongoing this summer of 2024, and completion is slated for April 2025.

  • The site will have new fire alarm panels and HVAC controls installed as part of the District Wide Fire Alarm Replacement & HVAC Controls Projects.
  • The tennis courts and baseball improvement work is slated for completion in the summer of 2024.

  • Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.