Construction Updates

As of March, 2025

 

Summer Projects: 

  • The site will be without power for an estimated 4-week period while the new switchgear is installed.

  • The site will be on fire watch during the replacement of the fire alarms.

  • The parallel parking spaces along the fire lane entrance onto Alameda de las Pulgas will have two-way traffic of heavy machinery.

  • The site will have new fire alarm panels and HVAC controls installed as part of the District Wide Fire Alarm Replacement & HVAC Controls Projects.
  • Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.

Summer Projects: 

  • Construction of the new gymnasium is slated for completion late July / early August

  • Building C HVAC and roof replacement is slated to be completed at the end of summer 2025.
  • The site will have HVAC controls installed as part of the District Wide HVAC Controls Projects.
  • Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.
  • The stadium lights will be replaced with LED lighting and the track will not be accessible or available for use during construction.
  • The nutrition services department will be upgrading the school kitchen over the Summer.

Summary Projects:

  • Construction of the Solar Canopies and EV Charging Stations requires closure of the front entry of the school as a safety precaution.
  • HVAC Controls replacement postponed to Summer 2026.

Summer Projects: 

  • Replacement of the chillers on buildings J&K will impact ventilation and cooling.

  • The nutrition services department will be performing upgrades in the kitchen in the summer.

  • The site will be on fire wat through construction for the new fire alarm panels as part of the District Wide Fire Alarm Replacement Project.
  • The switchgear foundation will be poured Summer of 2025 and construction for the remainder of that work will continue Summer of 2026.
  • The Hillsdale HS monument project is in design and will have no impact to the site.

Summer Projects: 

  • The site will have new HVAC controls installed as part of the District Wide HVAC Controls Projects.
  • Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.
  • The nutrition services department will be performing upgrades in the kitchen in the summer.
  • The Switchgear Project is postponed to Summer2026.

Summer Projects: 

  • Construction of the new gym is slated for completion in May 2025.

  • The site will have new HVAC controls installed as part of the District Wide HVAC Controls Replacement Project.
  • The San Mateo High School Kiln Project will take place beginning June 2, 2025, and is slated for completion at the end of the Summer.
  • Construction of new solar arrays and EV charging stations will begin as part of the District Wide Solar PV & EV Charging Projects.
  • The parking stalls between the new gym and tennis courts will be re-striped.
  • The Bridge Academy Portables will be installed in May 2025.
  • The Venus and Saturn rooms will be modernized at the adult school during the Summer of 2025.
  • The transportation yard will be impacted by the installation of EV bus charging stations and install and energization of new switchgear.